WHAT’S BEEN HAPPENING AT KIN COLLECTION
After completing 80% of the concrete suspended slab and reinforcing steel installation, Beedie Construction continues the wood framing process.
Construction Progress
Ongoing
– Wood framing for Parkside Homes (level 1) complete
– Concrete suspended slab (level 1) 80% complete
– Underground parkade waterproofing
Completed
– Parkade slab-on grade concrete preparation
– Excavation
– Reinforcing steel installation