WHAT’S BEEN HAPPENING AT KIN COLLECTION
After pouring the concrete suspended slab on the north-west corner of the site, Beedie Construction has begun the wood framing process.
CONSTRUCTION PROGRESS
Ongoing
– Wood framing
– Concrete suspended slab preparation for level 1
– Reinforcing steel installation
– Electrical and mechanical rough-in
– Underground parkade waterproofing
Completed
– Parkade slab-on grade concrete preparation
– Excavation