As Beedie Construction continues the roofing and window installation process and wood framing of the homes, the installation of the exterior cladding,...
Upon completion of the structural steel installation and wood framing of our Parkside Homes, Beedie Construction continues the wood framing process. ...
After completing the concrete suspended slab and underground parkade waterproofing, Beedie Construction has begun wood framing of the homes....
After completing 80% of the concrete suspended slab and reinforcing steel installation, Beedie Construction continues the wood framing process....